The decisions of the Board were published in the current issue of the Official Gazette.
Accordingly, the storage tariff for the Mersin plant of the Opet Petrolcülcülük Company was renovated and approved. The company’s daily storage service fee for the Mersin plant, gasoline types and motorine 1.63 pounds per cubic meter, aviation fuel types were determined as 1.37 pounds.
Delivery fees to be collected per service was 81.35 pounds per cubic meter for gasoline types, 127.10 pounds for motorine types, 40.66 pounds for aviation fuel species.
EMRA, Pipe Lines and Petrol Transportation Inc. (BOTAŞ) Tuz Lake natural gas underground storage facility and Silivri underground natural gas storage facility will be implemented in 2025 storage tariffs.
In this context, the storage fees to be valid in 2025 were determined as 3,080123 pounds per standard cubic meter for the capacity cost of the upper limits, 0,105722 pounds for injection price and 0.010516 pounds for the reproduction price.
Ministry of National Defense Fuel Supply and NATO Pol Facilities Business Presidency of the two storage facilities in Antalya, the transmission tariff regarding the pipeline was also modified. Accordingly, the transmission price to be taken per service was 210.64 pounds per cubic meter for aviation fuel types.
– The upper limit of system usage fee was determined
Within the scope of the decisions of the EMRA, the upper limits of the system usage fee of some natural gas distribution companies to be valid as of April 1 were revised.
Accordingly, Aksa Gümüşhane Bayburt Natural Gas Distribution Inc.’s system usage fee according to the annual consumption amount of 0,220835 to 2,842758 pounds per standard cubic meter, Diyarbakır Natural Gas Distribution Inc.’s 0,888854 to 1,960069 pounds.
İGDAŞ İSTANBUL GAS DISTRIBUTION INDUSTRY AND TRADE AŞ’S System Use fee according to the annual consumption amount to be valid as of April 1, 0.093799 to 1,782808 pounds per cubic meter, Kızılcahamam Natural Gas Distribution Inc.’s system usage fee varies between 1,158314 to 2,68411414 pounds per cubic meter.
On the other hand, EMRA has determined the active electricity wholesale tariff to be implemented by Electricity Production (EÜAŞ) to be valid from 1 April. Active Electric Energy Wholesale Tariff will be applied to distribution companies as 225,0000 cents per kilowatt -salas in technical and non -technical loss energy sales to distribution companies.